Seamless IT Infrastructure Relocation for CIHP STEM Hub

Auxano relocated, reinstalled, upgraded, tested, labeled, and certified the CIHP STEM Hub infrastructure, including server rack systems, switching, wireless access points, IP telephony, UPS units, Synology storage, access control, CCTV, FM200, conference displays, and new cabling.

IT equipment relocation and data migration setup for CIHP STEM Hub

Challenge

The operating gap that needed attention

CIHP needed to move the STEM Hub to a new Ikeja location without compromising performance, security, safety, or operational readiness for ongoing digital and STEM programs.

Auxano Response

A structured rollout from assessment to handover

1

Dismantled existing ICT, security, and safety systems, transported equipment, and reinstalled the environment at the new facility.

2

Relocated server racks, switches, wireless access points, IP telephones, UPS units, Synology storage, temperature sensors, FM200, access control, CCTV, and conference displays.

3

Supplied and installed new LAN and CCTV cabling, fiber interconnects, patch panels, access points, cable management systems, raised flooring, earthing infrastructure, and supporting civil works.

4

Tested, labeled, and certified systems to confirm performance and operational readiness in the new location.

Result

What changed after the project

The STEM Hub moved into a fully functional and modernized technology environment with continuity across networking, security, fire suppression, storage, collaboration, and support systems.

2 months

December 2024 to January 2025

10+

Systems relocated and recommissioned

0 compromise

Performance and readiness objective

Related Capabilities

The service areas behind this outcome

These service areas show the practical delivery capabilities behind the project outcome.

computer installation setup
network cabling
office telephone system ip pbx
surveillance system cctv
door access control
data centre services

More Proof

Related case studies

View all
Structured network rack cabling for CIHP headquarters ELV infrastructure

Centre for Integrated Health Programs (CIHP)

Standards-Compliant ELV Infrastructure for CIHP Headquarters

Auxano delivered a complete Extra-Low Voltage infrastructure foundation covering structured LAN cabling, CCTV cabling, fiber backbone components, cable management, underground pathways, and FM200-ready fire suppression pipework.

Healthcare and Development ProgramsAbuja, Nigeria
View case study
Compliance and security infrastructure environment for Fringe PCI DSS upgrade

Fringe

PCI DSS-Aligned ICT Infrastructure Upgrade for Fringe

Auxano consolidated server virtualization, network redesign, firewall deployment, wireless expansion, endpoint upgrades, access control, surveillance enhancement, cloud backup, and IT support into one compliance-focused infrastructure program.

Financial Services and Regulated OperationsNigeria
View case study

Next Step

Need this kind of result in your own environment?

Share the site, system, or operational challenge and Auxano can shape the right assessment, rollout, and support plan.

Book consultation